beautypg.com

0 installation, 1 wiring, 2 initial installation – Rockwell Automation 61C501 AutoMax/AutoMate 115V Input Module User Manual

Page 11

background image

3Ć1

3.0 INSTALLATION

This section describes how to install and remove the module and its

cableassembly.

3.1

Wiring

Theinstallation of wiring should conform to all applicablecodes.
To reduce the possibility of electrical noise interfering with the proper

operation of the control system, exercise care when installing the

wiring from the system to the external devices. For detailed

recommendations refer to IEEE 518.

3.2

Initial Installation

Usethefollowing procedureto install themodule:
Step 1.

Turn off power to the system. All power to the rack as well

as all power to thewiring leading to themoduleshould be

off.

Step 2.

Mount the terminal strip (M/N 57C370, 61C505, or

61C506) on a panel. The terminal strip should be mounted

to permit easy access to the screw terminals. Make certain

that theterminal strip is closeenough to therack so that

the cable reaches between the terminal strip and the

module.

Step 3.

Fasten field wires to the terminal strip. Typical field

connections for 115 V AC inputs areshown in figure3.1.
Refer to Appendix C for the arrangement of terminal board

connections. Make certain that all field wires are securely

fastened.