Filling a Prepared Space in a Medium Voltage Controller Line-up with DeviceNet

8-3

1500-IN057

C-EN-P – June 2013



Figure 8.3 – Typical Starter Kit LV Panel for DeviceNet (lower unit of 2-High)


Procedure for Bottom Unit

Note:

This procedure does not require the top unit to be temporarily

disconnected from DeviceNet.

The prepared space does not have any DeviceNet connections or any

DeviceNet wiring entering or crossing the unit.

The vertical flat cable assembly on the low voltage panel of the kit has a

port to which a round cable is connected. The round cable is provided

with a 5-terminal connector on its loose end. Once the controller kit has

been installed, the DeviceNet connections may be completed. Connect

the loose end of the round cable to the bottom port of the upper low

voltage panel. If a device is already connected to the lower port of the

upper panel, a splitter or ―Y‖ connector (part number 40122-304-51)

must be inserted into this port to accommodate the cable connection to

the lower low voltage panel.