Step 1: install first row of main tees – USG One-Directional Curvatura 3-D System User Manual

Page 2

background image

Page 2 of 12

1.

1.

1.

1.

1.

1.

1.

1.

1.

Each hanger wire should fall in line with
a pre-punched hanger hole. Because
the tees are curved, the space between
hanger wires will vary along the main tee.

It’s best to start at a point near a wall
or column that can be used for reference
and support.

Refer to the bill of material and ribbon
drawing and locate the appropriate
flush-cut main tee to start the first row
of main tees.

For your reference, part ID codes are
listed on the ribbon drawing and stamped
on the ends of each main tee.

One-Directional C

urvatura

Installation Instructions

Step 1: Install First Row

of Main Tees

Main tees may require field punched
hanger holes several inches from their
termination to allow adequate support
and leveling capabilities

Find a corner starting point based on
locations specified on your architect’s
plans or by scaling from a working
drawing.

Lay the main tees out on the ground as
they will be arranged in the installation.

Establish where each hanger wire will
be attached.

Once you have established where each
hanger wire should go, pre-hang the first
row of hanger wire.

A.

B.

C.

D.

E.

F.

G.

H.

I.

Step 1:

Install First Row