Step 2: main tee installation – USG Topo Ceiling System User Manual
Page 3

Page 3 of 12
T
OPO
Ceiling
System
Installation
Instructions
48"
24"
A.
B.
C.
D.
F.
G.
H.
I.
Find a starting point based on a corner
location specified on the architect’s plans
or by scaling from a working drawing.
Mark the hanger wire locations…
…and lay out the Main Tees as shown
on the 2-D plan, aligning them with the
hanger wire locations.
Mark the hanger wire locations on the
Main Tees as they are shown on the
drawing plan.
In cases when a Main Tee is required
2 feet from an adjacent Main Tee, it will
be hung at a different elevation. Refer
to the 3-D drawing for the proper height.
Establish the location of the highest point
of the assembly as specified by the archi-
tect. Be sure to have at least 2 inches of
clearance above this point to prevent inter-
ference with installation of the Edge Trim.
Once the vertical placement is determined,
install and bend the hanger wires as
indicated on the 3-D drawing. Then, hang
the first Main Tee.
Main Tees are connected with Main Tee
Splice Clips.
Main Tees are hung from the high points,
on 4-foot centers. They are usually
spaced 4 feet apart and are hung at the
same elevation.
E.
Step 2: Main Tee Installation
- Securock Gypsum-Fiber Roof Board (2 pages)
- BEADEX Lightweight Setting-Type Joint Compounds (2 pages)
- BEADEX Wall and Ceiling Spray Texture FASTEX (1 page)
- BEADEX Quick Spray Decorative Texture (1 page)
- C2 Paired Compasso Channels (12 pages)
- Casting Fireplace Surrounds (32 pages)
- Ceiling System (2 pages)
- Ceiling Retail (8 pages)
- Compositions Decorative Clouds (8 pages)
- DIAMOND Finish Plasters (6 pages)
- DIAMOND Veneer Basecoat Plaster (4 pages)
- DONN Ceiling (8 pages)
- DONN Suspended Ceiling (4 pages)
- DRYSTONE Casting Media Mixing Procedures (2 pages)
- Durock Tile Membrane (7 pages)
- Durock Shower System (16 pages)
- Domed Ceilings and Barrel Vaults (12 pages)
- Drying Plaster Casts (4 pages)
- ENVIRO-SHIELD Bonded Fiber Matrix Application Rates (3 pages)
- Exposed Hanger Solutions (4 pages)
- Fiberock Underlayment and Tile Backerboard (12 pages)
- FIBEROCK Interior Panels Abuse-Resistant (3 pages)
- FIBEROCK Interior Panels AQUA-TOUGH (2 pages)
- Firecode Compound (2 pages)
- Finishing and decorating glass-Mat gypsu M panels (3 pages)
- HYDROCAL Gypsum Cements (2 pages)
- IMPERIAL Basecoat Plaster (4 pages)
- IMPERIAL Gypsum Base (2 pages)
- IMPERIAL Interior Ceiling Gypsum Base Sag-Resistant (2 pages)
- Industrial Plasters and Gypsum Cements for Foundry Applications (1 page)
- Levelrock Floor Underlayment Finished Floor (16 pages)
- Manufactured Housing Handbook (29 pages)
- Metal Ceiling Panels Celebration, Geometrix, Panz, and Paraline (2 pages)
- Moisture, Mold, and Construction Practices Frequently Asked Questions (4 pages)
- Moisture, Mold, and Construction Practices Repairing Water-Damaged Building Systems (2 pages)
- Pixels Wall Mounted (36 pages)
- Plank and Large Panel Stabilizer Bars (16 pages)
- Plasters and Gypsum Cements for the Ceramic Industry (6 pages)
- RED TOP Finish Plaster (1 page)
- RED TOP Gauging Plaster (1 page)
- Structo-Crete Structural Concrete Panel (9 pages)
- Structo-Crete Structural Concrete Panel (2 pages)
- Structo-Crete Structural Concrete Panel (1 page)
- Securock Glass-Mat Sheathing (4 pages)
- Roof Board Applications (3 pages)