beautypg.com

Ductwork, Duct insulation and vapor proofing, Motors and drives – Titus VAB IOM User Manual

Page 4: Sound attenuation, Electrical connections, Condensate drain, Installation, Vab installation manual

background image

VAB Installation Manual

IOM-VAB-00

06-30-04

4 of 7

Installation

Basic installation procedure covers verifying and/or

installing the following items.

Ductwork

Duct insulation and vapor proofing

Motors and drives

Sound attenuation

Electrical connections

Condensate drain

Water piping

Ductwork

Use accepted industry practices and design guidelines of

the ASHRAE Fundamentals Handbook. Ductwork must

comply with all building codes and the National Fire

Protection Association’s pamphlet 90A and 90B.
Carefully inspect any previously installed ductwork to

determine suitability.

Note: Ductwork should be of a size meeting

requirements of the installation. Ductwork should

transition gradually from a smaller size blower outlet to

required duct run size to avoid excessive loss of air

velocity.

When return air duct connection is smaller than return air

inlet opening, construct the transition piece so the vertical

and horizontal dimensions of transition do not increase

more than one inch for every seven inches of length.
Allow a minimum of three feet of straight ductwork

following an equipment outlet.

Duct Insulation and Vapor Proofing

Previously installed heating supply ductwork may already

have adequate insulation against excessive heat loss.

This insulation may be satisfactory for protection against

heat gain from summer cooling. Depending upon

application, additional insulation may be required.
Externally insulated ductwork must have adequate vapor

seal for summer operation, especially where duct is

exposed to high humidity conditions.

Motors and Drives

Units are normally shipped with motor and drive installed.

However; when mounting a motor on the adjustable base

in the field, use extreme care to ensure proper alignment

and belt tension.

Sound Attenuation

Flexible duct connections should be used between the unit

and both the supply and return ducts.

Electrical Connections

Each unit has a mounted control box, and typically, the

motor is to be wired to this box. Only ODP, single- and

three-phase motors on 800 to 2000 CFM units are factory-

wired to junction box. All other motors require field wiring

to junction box located on side of the unit cabinet.

Note 1: Unit must be permanently grounded in

accordance with NEC and local codes and ordinances.

See the typical wiring diagrams shown in Figure 5.
Note 2: Not all installations require a starter (some

motors utilize a contactor).

Figure 5. Wiring Diagrams