liftinG prOcedure

liFTing THe Screed

The following procedure and Figure 1 describe how to lift

the vibratory screed.

1. Attach the U-shaped hanger and associated hardware

to the top of each truss frame section as shown in

Figure 1. Tighten hanger securely so that it will not slip.

Warning

never lift the screed to unnecessary heights.

alWayS make sure that no one is standing underneath

the screed while it is being lifted.

2. Utilize a spreader bar of proper length and lifting

capacity. Secure lifting straps from both ends of the

spreader bar to the attached lifting hangers.

3. Connect lifting cables from the spreader bar to the

lifting hook of a crane or forklift. Ensure that the lifting

hook and chain are of appropriate lifting capacity.

4. Use crane or forklift to hoist screed onto a flatbed truck

for transporting or onto the form for screeding.

Figure 1. Lifting the Screed

FRONT