Moving Frames and Integrated Operations Platform
Installation
Moving Frames and Integrated Operations Platform
The packing materials may shift and loosen while moving the frame.
Moving the frame with loose packing materials may cause injury to
personnel and damage to the frame.
Remove the packing materials before moving the frame.
Note
Before the FSE arrival, it is the customer’s responsibility to arrange the
off-loading, unpacking, and moving of the testing system to the final site
location.
Note
If the testing system needs to be moved to another location after initial
installation, it is the customer’s responsibility to move and remount the
system.
Machine Location and Ventilation
To ensure proper ventilation, locate the load frame approximately 100 mm (4 in)
away from adjacent walls and equipment. Do not block the vent holes of the
machine.
For comfortable working conditions and proper equipment operation, heat
dissipation of the equipment must be considered in providing adequate heating or
air conditioning in the laboratory area. Heat dissipation can be approximated by
summing the heat losses going into the room (1 kVA is equivalent to 860 kcal/hr
[3,400 Btu/hr]) and the gains from other sources such as furnaces and personnel.