Commissioning
Commissioning for 9300 series standard devices
EDKMF2102 DE/EN/FR 7.1
78
l
Inbetriebnahme93XX
Detailed
information
Procedure
Step
4.
Make other necessary controller settings.
W Commissioning of the controller
Documentation
for the respective
controller
l
For initial commissioning set code C0005 = 1011 (signal
configuration: speed control via AIF).
l
Enable the controller.
– Terminal 28 (RFR: controller enable) is always active and has
to be HIGH during operation. Otherwise the controller will be
inhibited.
l
Select the speed setpoint with C0141 in % of n
max
(value in
C0011).
Note
With the signal configuration C0005 = xx11, terminal A1 is switched
as a voltage output. This means that only the following terminals
should be connected:
l
X5.A1 to X5.28 (Controller enable)
l
X5.A1 to X5.E1 (Clockwise rotation / QSP)