beautypg.com

6 commissioning, 1 before initial switch-on, Commissioning – Lenze E84AYCPM User Manual

Page 30: Before initial switch-on, 6commissioning

background image

Lenze · E84AYCPM communication module (PROFIBUS®) · Communication Manual · DMS 5.0 EN · 11/2012 · TD17

30

6

Commissioning

6.1

Before initial switch-on

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

6

Commissioning

During commissioning, plant-specific data such as motor parameters, operating parameters,

responses, and parameters for fieldbus communication are defined for the inverter. Lenze devices

use codes for this purpose.
The codes of the inverter and for communication are saved to the memory module in a non-volatile

data set.
In addition, there are codes for diagnosing and monitoring the stations.

Parameter reference

( 95)

6.1

Before initial switch-on

Stop!

Before switching on the inverter for the first time, check ...

• the entire wiring for completeness, short circuit and earth fault.
• whether the bus system is terminated by means of a bus terminating resistor at the

first and last physical bus station.

Activating the bus terminating resistor

( 27)