ERICO SIM Series Terminal Elevation: 4m Above Structure User Manual
Erico dynasphere mkiv, Detail "a
1m
INTCPT ADAPTER
(ERICO Part # INTCPTMIDYN)
ERICO DYNASPHERE
(ERICO Part # D/SMKIV-SS)
®
Detail "A"
Stainless Steel Mast
(ERICO Part # SIM28A2)
Bonding Clamp
(ERICO Part # TMCSS)
SIM28A2
1
-
®
Ground Inspection Well
Downconductor
Lightning Event Counter
(ERICO Part # LECIV)
ERICO CADWELD Connection
or mechanical connection
®
®
3m tape enclosed in
GEM material
Minimum 16mm X 2.4m long
ground rod in four locations
Stainless Steel Cable Tie
(ERICO Part # CABTIESS)
Three every 1m
Lightning Event Counter
Refer to installation manual
for alternate locations
(ERICO Part # LECIV)
Two downconductors
are required
Not to Scale
Downconductor
TMCSS Mast Clamp
Installing contractor to
field adjust and insure a
secure bond on highest
SIM series mast
For complete
grounding system
refer to Detail "A"
Typical Conductor Connection
(ERICO Part # PDCUC) Tape Fasteners
(ERICO Part # TCEC253) Copper Tape
Not to Scale
3
-
Crow's Foot
(ERICO Part # GF302)
Stainless Steel Mast
(ERICO Part # SIM33B3)
Mast Support Bracket
(ERICO Part # ALOF1GS)
SIM33B3
-
2
Mast Detail
2 Holes, 10.9mm
39.9mm
89.9mm
119.9mm
Not to Scale
Typical ALOF1GS Wall Bracket Base
2
-
End View
3
-
1
-
Suggested triangular grounding system for each downconductor:
The grounding system shown in the detail is a suggested layout. Each radial consists of a trench
approximately 0.8m deep. The conductor is laid in the trench and is connected to ground rods. The
conductor in each trench is encased in GEM material. Ground rods must extend 3m below ground
level.
Note: This is one of several alternative installation methods.
Refer to ERICO installation manual for more details.
1m
TECHNICAL SUPPORT
www.erico.com
IP79153_A
1 OF 1
INSTRUCTION SHEET
CADDY, CADWELD, CRITEC, ERICO, ERIFLEX, ERITECH, and LENTON are registered trademarks of ERICO International Corporation.
WARNING:
ERICO products shall be installed and used only as indicated in ERICO product instruction sheets and training materials. Instruction sheets are available at
1.
www.erico.com and from your ERICO customer service representative.
ERICO products must never be used for a purpose other than the purpose for which they were designed or in a manner that exceeds specified load ratings.
2.
All instructions must be completely followed to ensure proper and safe installation and performance.
3.
Improper installation, misuse, misapplication or other failure to completely follow ERICO's instructions and warnings may cause product malfunction, property
4.
damage, serious bodily injury and death.
SAFETY INSTRUCTIONS:
All governing codes and regulations and those required by the job site must be observed.
Always use appropriate safety equipment such as eye protection, hard hat, and gloves as appropriate to the application.
ERICO DYNASPHERE MKIV