beautypg.com

Electrical connections, L1 l2 – CHAMPION IUH351 User Manual

Page 9

background image

3

1. Refer to the connection diagram on the preceding page and the photo below:
2. Machines require a 2-wire plus ground supply which includes a current carrying neutral.
3. Power connections are made at the Main Terminal Block (MTB).
4. The MTB is located on the left-rear corner of the electrical panel behind the front access panel.

(See the illustration on the previous page.)

Installation

Electrical Connections

1. Remove the lower front access panel of the dishwasher.
2. Locate the electrical mounting panel on the right-side of the machine.

Remove the retaining nut at the top of the panel that holds the panel in place.

3. Lower the panel and pull it forward to gain access the MTB.
4. Feed the power cable through the cable hole located

on the right side, as viewed from the front of the machine,

into the interior of the machine.

5. Make sure the cable passes through the cable mounting

bracket located near the front-center of the

base and secure the cable with a cable connector.

6. Connect the ground wire to the base of the dishwasher

with the ground screw provided next to the

cable mounting bracket.

7. Feed the remaining cable wires to the Main Terminal

Block and connect according to the connection

diagram to the right.

To Connect Main Power to the Dishwasher:

NOTE:

Provide a 3 foot service loop in the power cable at the back of the dishwasher for service.

L1

L2

208-240

VAC

GRD

SINGLE PHASE POWER CONNECTION

208-240VAC 50/60/1

HOW TO CONNECT POWER

1. Check the data plate on the front of the

dishwasher for the voltage of the machine.

2. Remove the lower-front access panel.

3. Lower the electrical component bracket.

4. Feed the power cable from the rear of the

dishwasher to the center of the machine

and through the cable bracket.

5. Connect the ground wire to the base of the

dishwasher using the ground screw located

near the bracket.

6. Feed the power leads to the terminal block.

7. Connect L1, L2 and ground.

8. Main Power connections are complete.

To Main Terminal Block

From Rear of Machine

L1

L2

GRD

Cable Bracket

Route the supply cable through the cable bracket.