45
Check that the pumps and final rinse shut-off before the object reaches the
conveyor shut-off shelf.
Check that the conveyor belt stops when the object pushes the conveyor shut-off
shelf.
Move the shut-off shelf toward the tunnel of the machine. The conveyor belt will
start moving again.
Push the RED stop button. The conveyor belt will stop moving.
Flip the power switch on the control cabinet to OFF. The red power light will go out.
Open all the drain valves and check that the house drains can handle the flow.
Remove any protective film from the stainless steel and install the side panels and
chain guard.
Check the curtains for correct placement in the machine.
Be sure the short flaps of the Long Curtains face the load end of the machine.
Check the spray pipes.
Be sure the spray pipe gasket is installed on the end of spray pipe before installing.
Spray pipes are installed by inserting the pipe into the coupler and turning 1/4 turn
clockwise.
Check the scrap screens.
Install any scrap basket covers.
Check that the conveyor shut-off shelf is pushed toward the machine tunnel.
Close the drain valves, located under the base of each tank.
When the drain handle is horizontal, the valve is open.
When the valve handle is vertical, the valve is closed
Check the detergent and rinse aid supplies (supplied by others).