Installation, Installation -14, Track roller required tools - removal -14 – JLG 600SC_660SJC ANSI Service Manual User Manual
Page 118
![background image](/manuals/552315/118/background.png)
SECTION 6 - UNDERCARRIAGE
6-14
– JLG Lift –
3120794
Installation
1.
Be sure the mounting surface on the track roller, the
track guide, and the undercarriage frame are clean
and free of dirt and debris prior to installing the track
roller and the track guide.
2.
Use tooling (B) to put the track roller (2) in position
on the undercarriage frame. The weight of the track
roller is 75 lb. (34 kg). Make sure the plug in the
roller is facing toward the outside of the undercar-
riage frame. Install the four bolts that hold the roller
in position.
3.
Use tooling (B) to put track guide (1) in position on
the undercarriage frame. The weight of the track
guide is approximately 110 lb. (50 kg). Install the
four bolts that hold the guide.
4.
Prior to lowering the machine to the ground and
tightening the track, be sure that all of the track roll-
ers rotate smoothly by hand.
5.
Lift the machine off tooling (A). Remove tooling (A)
from the machine. Lower the machine to the floor.
6.
Tighten the tension of the track.
Table 6-5. Track Roller Required Tools - Removal
Tool
Part #
Description
Qty.
A
8S-7640
Stand
2
8S-7611
Tube
2
8S-7615
Pin
2
B
FT-1310
Track Roller Lifting Fork
1