Chapter 2: Installation

46

Installing an SFP Transceiver

The AT-FS750/24POE WebSmart Fast Ethernet Switchhas four SFP
combo ports. Perform this procedure before “Cabling and Powering On
the Switch” on page 48.

To install an SFP transceiver, perform the following procedure:

Note

The transceiver can be hot-swapped; you do not need to power off
the switch to install an SFP transceiver. However, always remove
the cables before removing the transceiver.

Note

You must install an SFP transceiver before you connect cables to it.

1. Remove the transceiver from its shipping container and store the

packaging material in a safe location.

2. Remove the dust plug from the SFP slot, as shown in Figure 14.

Figure 14. Removing the Dust Plug from the SFP Slot

3. Locate the label on the transceiver and turn it so that the label is on top

and the alignment groove is on the bottom.