beautypg.com

Dedicated lo100c management port module option – HP ProLiant DL120 G5 Server User Manual

Page 29

background image

Hardware options installation 29

5.

Install the battery.

6.

Route the cable ("

Battery cabling for BBWC

" on page

32

).

7.

Connect the cable to the cache module.
For clarity, the server is not shown in this illustration.

8.

Install the primary access panel.

9.

Install the server into the rack.

Dedicated LO100c management port module option

To install the component:

1.

Power down the server (on page

6

).

2.

Remove the server from the rack (on page

6

).

3.

Remove the primary access panel (on page

7

).