Process connection and entry pipe


Caution:

Do not put the nozzle close to the entry pipe. Pouring the product directly onto the
probe will give false readings. Install deflector plate if impossible to distance gauge
from entry pipe.



Stilling wells

Tanks with floating roofs for petro-chemical applications: use a stilling well.

1 Stilling

well

2 Tank

3 Floating

roof

4

Product (petroleum applications)

5

Well fixed to tank base (no roof
deformation)

6 Sediment




1.3.3 Installation

instructions: Gauge - all applications


BM102 gauges are designed to be mounted on a suitable process connection on a tank or sump.
Install the gauge using two people to avoid damaging the probe. Support the housing and the
probe.