beautypg.com

Zrc top load rebuild procedure – Warner Electric ARC Clutch_ZRC Top Load User Manual

Page 11

background image

Warner Electric • 800-825-9050

P-2019 • ARC 11

Remove grease zerk using open-end wrench. See
Figure 47.

Figure 48

ZRC

Top Load Rebuild Procedure

Remove spring adjustment rings using two
spanner wrenches (YTL3-0009) and soft hammer.
See Figure 48.

Figure 49

Remove upper spring cover(if applicable), spring,
and lower spring cover (if applicable) from top-
load assembly. See Figure 49.

Figure 50

Place top-load in vice, clamping on flats. Using
YTL3-0005 and a soft hammer, loosen spindle
adapter (if applicable) and remove. See Figure 50.

Figure 51

Continue to hold top-load in vice, clamping on flats.
Using a socket and breaker bar, loosen the nut
inside top-load assembly. See Figure 51.

Figure 52

Remove the nut inside top-load assembly. See
Figure 52.

Figure 53