Installing the phase sensors, Parts provided for ct installation per pole, Ct post mounted in the breaker back frame – GE Industrial Solutions ProTrip Conversion Kits AK-1-50 User Manual
Page 7
Installing the Phase Sensors
Figure 5 shows the parts provided for assembly of the CT
on each pole.
1. Mount the new copper CT post to the back frame
with the two
3
/
8
-16 x 1
1
/
2
" bolts, flat washers, and
lock washers provided, as shown in Figure 6.
2. Fasten the three small insulated wire fasteners to the
back frame with the
1
/
4
-20 x 1
3
/
4
" screws provided,
as shown in Figure 7. One fastener is mounted under
each CT.
3. Place a CT over each copper post, first applying a
small amount of RTV or similar adhesive to prevent
the CTs from rotating.
4. Mount the top copper bus over each CT and secure
with the
1
/
2
-13 x 1
1
/
2
" Allen-head bolts, lock washers,
and flat washers provided.
5. Insert two
3
/
8
-16 x 1
1
/
2
" bolts, lock washers, and flat
washers through each top copper bus into the
contact arm assembly.
6. Tighten the
3
/
8
-16 bolts to 200 in-lb and the
1
/
2
-13
bolts to 300 in-lb.
WARNING: Step 6 ensures critical electrical integrity
connections. The designated bolts must be correctly
tightened for proper operation. Failure to tighten these
bolts properly will cause a breaker failure, resulting in
property damage and/or personal injury.
Figure 5. Parts provided for CT installation for one pole.
Figure 6. CT post mounted in the breaker back frame.
Figure 7. CT installation completed..
7