GE Industrial Solutions A Series Lighting Control Panelboards Installation User Manual
Page 3

3. Remove dead front shield in preparation of wiring the line and branch breakers of the interior. Keep
mounting screws handy for re-assembly. Secure line side wires and load wires to branch breakers neutral
lugs if service requires and ground connections using the tightening torque specifications in table 2 below.
TABLE 2
TORQUE VALUES FOR
PANELBOARD HARDWARE
SCREW SIZE
TORQUE
(IN-LBS)
#4 STEEL
16
#10 PLASTIC
16
#8 CU/ AL/STEEL
24
#10-32 CU/ AL/STEEL
32
1/4-20 AL/<.150 THICK CU
44
1/4-20 .150 THICK CU
60
5/16-18 CU/ AL/STEEL
110
3/8-16 CU/AL/STEEL
220
1/2-13 CU/AL/STEEL
220
4. Refer to address chart provided with rating booklet DEH40007 and record load locations in preparation for
setting load-scheduling times into the programmable controller. Refer to instruction DEH41080 for proper
controller installation and wiring diagrams.
16 External Inputs (under cover)
Input power (removal terminal)
RS 485
Note:
Controller is powered internally. No control power
is required.
Power in control box is class II low voltage.
Electro static discharge sensitive. The installer
should be grounded when handling controller.
Service port
RS 485 Subnet
Dry Contact output
Ethernet
Dipswitches (under cover)
4 REMOVABLE 1 / 2 INCH KNOCKOUT
PLUGS PROVIDED 2 PER SIDE FOR
OVERRIDE TERMINALS
Analog Input
Local Override Input
2 REMOVABLE 1 / 2 INCH
KNOCKOUT PLUGS PROVIDED
FOR PERMANENT CONTROL
AND ETHERNET WIRING.
RS 232
Battery (under cover)
PANASONIC CR2032 (3V)
or equiv.
For protection of control wire between control box and
panel box options include:
1) Shrink tubing sleeve rated for 600V
2) Flexible metal or non-metallic conduit
3) GE kit catalog No. ASRGLCCWT
- 3 -