Installation, Chapter 6 installation, Sidewall erection – Grain Systems Tanks PNEG-1093 User Manual

Page 28: Sidewall erection instructions, Overlapping panels

background image

28

PNEG-1093 2.66" Corrugation Unstiffened Bin

6. Installation

Sidewall Erection

Sidewall Erection Instructions

Gauge Color Code

1. Before bolting the sidewall sheets together, check that you have the proper gauge steel for the first

ring. The higher gauge numbers denote the thinner materials. (For example, 20 gauge material is
thinner than 14 gauge.)

2. In erecting most grain bins, the thinnest material usually goes on top, therefore the first sidewall ring

you assemble will be the top ring of the bin.

3. Check the various gauges of the bin with the color code chart and begin building accordingly.

REMEMBER..... Assemble the top ring first.

Overlapping Panels

1. Once you have selected the proper gauge material, begin assembling all sidewall sheets in the

following manner: Standing on the inside of the bin, place the left panel to the inside with the right
panel to the outside.

(See Figure 6A.)

Check to see that the sidewall sheet is “Right Side Up”.

Figure 6A

Gauge

Color Code

20

Red

19

Black/Yellow

18

Orange

17

Pink/Light Blue

16

Blue

15

Brown/Red

14

Green

13

Yellow/Blue

12

Black

11

Pink

10

Light Blue

9

Blue/Orange

8

Yellow

6

White

5

Fluorescent Green