background image

Venting Installation Tips

Support piping:

horizontal runs—at least every 5 ft

vertical runs—use braces

under or near elbows

Venting Configurations

For heaters connected to gas vents or chimneys, vent

installations shall be in accordance with the NFGC

(U.S.), or B149 (Canada), or applicable provisions of

local building codes.

Natural Draft Vertical Venting

(Category I)

Installation

Natural draft venting uses the natural buoyancy of the

heated flue products to create a thermal driving head

that expels the exhaust gases from the flue. The nega-

tive draft must be within the range of -.01 to -.08 in.

WC as measured 12 in. above the appliance flue out-

let to ensure proper operation. Vent material must be

listed by a nationally recognized test agency.

The maximum and minimum venting length for Cate-

gory I appliances shall be determined per the NFGC

(U.S.) or B149 (Canada).

24

1. Vent must terminate at least 4 ft below, 4 ft hori-

zontally from or 1 ft above any door, window or

gravity air inlet to the building.

2. The vent must not be less than 7 ft above grade

when located adjacent to public walkways.

3. Terminate vent at least 3 ft above any forced air

inlet located within 10 ft.

4. Vent must terminate at least 4 ft horizontally, and

in no case above or below unless 4 ft horizontal

distance is maintained, from electric meters, gas

meters, regulators, and relief equipment.

5. Terminate vent at least 6 ft away from adjacent

walls.

6. DO NOT terminate vent closer than 5 ft below roof

overhang.

7. The vent terminal requires a 12 in. vent terminal

clearance from the wall.

8. Terminate vent at least 1 ft above grade, including

normal snow line.

9. Multiple direct vent installations require a 4 ft

clearance between the ends of vent caps located

on the same horizontal plane.

Canadian Installations

Refer to latest edition of the B149 Installation code.

A vent shall not terminate:

1. Directly above a paved sidewalk or driveway

which is located between two single-family dwell-

ings and serves both dwellings.

2. Less than 7 ft (2.13 m) above a paved sidewalk or

paved driveway located on public property.

3. Within 6 ft (1.8 m) of a mechanical air supply inlet

to any building.

4. Above a meter/regulator assembly within 3 ft (915

mm) horizontally of the vertical centre-line of the

regulator.

5. Within 6 ft (1.8 m) of any gas service regulator

vent outlet.

6. Less than 1 ft (305 mm) above grade level.

7. Within the 3 ft (915 mm) of a window or door which

can be opened in any building, any non-mechani-

cal air supply inlet to any building or the

combustion air inlet of any other appliance.

8. Underneath a verandah, porch or deck, unless the

verandah, porch or deck is fully open on a mini-

mum of two sides beneath the floor, and the

distance between the top of the vent termination

and the underside of the verandah, porch or deck

is greater than 1 ft (305 mm).

WARNING: Examine the venting system at least

once a year. Check all joints and vent pipe

connections for tightness, corrosion or deterioration.

WARNING: The Commonwealth of Massachusetts

requires that sidewall vented heaters, installed in

every dwelling, building or structure used in whole or

in part for residential purposes, be installed using

special provisions as outlined on page 53 of this

manual.