beautypg.com

Raypak 302B-902B User Manual

Page 42

background image

42

The stainless steel direct vent cap must be furnished

by the boiler manufacturer in accordance with its list-

ing (sales order option D-15).

Use only double-wall vent pipe and the special gas

vent pipes listed for use with category II or IV gas burn-

ing boilers, such as the stainless steel Saf-T vent by

Heat Fab Inc. (800-772-0739), Protech Systems Inc.

(800-766-3473), Z-Flex (800-654-5600) or American

Metal Products (800-423-4270). Pipe joints must be

positively sealed. Follow the vent manufacturer’s

installation instructions carefully.

Direct Vent - Horizontal Through-

the-Wall

Installation

These installations utilize the boiler-mounted blower to

draw combustion air from outdoors and vent combus-

tion products to the outdoors.

The total length of the direct vent through-the-wall

exhaust vent cannot exceed 40 ft in length for the flue

outlet. Each elbow used is equal to 10 ft of straight

pipe. This will allow installation in one of the three fol-

lowing combinations:

40’ of straight flue pipe

30’ of straight flue pipe and one elbow

20’ of straight flue pipe and two elbows

The total length air supply duct cannot exceed the dis-

tances listed. Each elbow used is equal to 10 ft of

straight pipe. This will allow installation in one of the

three following combinations:

• 40’ of straight combustion air pipe

• 30’ of straight combustion air pipe and one elbow

• 20’ of straight combustion air pipe and two elbows

The flue exhaust direct vent cap is not considered in

the overall length of the venting system.

Care must be taken during assembly that all joints are

sealed properly and are airtight.

The vent must be installed to prevent the potential ac-

cumulation of condensate in the vent pipes. It is

recommended that:

1. The vent must be installed with a slight downward

slope of not more than 1/4 inch per foot of hori-

zontal run to the vent terminal.

2. The vent must be insulated through the length of

the horizontal run.

For installations in extremely cold climate, it is rec-

ommended that:

1. The vent must be installed with a slight upward

slope of not more than 1/4 inch per foot of hori-

zontal run to the vent terminal. In this case, an

approved condensate trap must be installed per

applicable codes.

2. The intake vent must be insulated through the

length of the horizontal run.

Common Venting System

Common venting of Category IV systems is not al-

lowed.

The stainless steel flue exhaust direct vent cap must

be furnished by the boiler manufacturer in accordance

with its listing (sales order option D-15).

Use only double-wall vent pipe and the special gas

vent pipes listed for use with category II or IV gas burn-

ing boilers, such as the stainless steel Saf-T vent by

Heat Fab Inc. (800-772-0739), Protech Systems Inc.

(800-766-3473), Z-Flex (800-654-5600) or American

Metal Products (800-423-4270). Pipe joints must be

positively sealed. Follow the vent manufacturer’s

installation instructions carefully.

Fig. 40: Direct Vent - Horizontal Through-the-Wall

WARNING: No substitutions of flue pipe or vent

cap material are allowed. Such substitutions would

jeopardize the safety and health of inhabitants.