beautypg.com

Raypak 302B-902B User Manual

Page 15

background image

15

5. Remove all plumbing fittings to the header. This

will include both inlet and outlet water pipe unions

and the pressure relief valve and drain piping.

6. Remove limits, control bulbs and/or thermocou-

ples.

7. Remove the six flange nuts and the in/out header

from the left-hand side.

8. Remove the six flange nuts and the return header

from the right-hand side.

9. Remove the header stud bolts from each tube

sheet.

10. Reverse the headers and stud bolts to the new

location.

11. Install NEW red beveled O-rings flush against both

tube sheets with the bevel facing outward.

12. Push the header firmly against the O-rings. Install

and tighten the flange nuts onto the stud bolts until

finger tight.

13. Slowly tighten the flange nuts, starting from the

center nut (number 1) in Fig. 9 and working se-

quentially around the header as indicated. Torque

all nuts to 25 ft/lb. DO NOT OVER-TIGHTEN.

14. Re-route the capillary(s), wiring etc. to the new

location, adding thermal paste and shim to the

capillary well.

Fig. 9: Torque Sequence

Relief Valve Piping

WARNING: Pressure relief valve discharge piping

must be piped near the floor and close to a drain to

eliminate the potential of severe burns. Do not pipe

to any area where freezing could occur. Refer to

local codes.

Hydrostatic Test

Unlike many types of heaters, this heater does not re-

quire hydrostatic testing prior to being placed in

operation. The heat exchanger has already been fac-

tory-tested and is rated for 160 psi operating pressure.

However, Raypak does recommend hydrostatic test-

ing of the piping connections to the heater and the rest

of the system prior to operation. This is particularly

true for hydronic systems using expensive glycol-

based anti-freeze. Raypak recommends conducting

the hydrostatic test before connecting gas piping or

electrical supply.

Leaks must be repaired at once to prevent damage to

the heater. NEVER use petroleum-based stop-leak

compounds.

To perform hydrostatic test:

1. Connect fill water supply. With bleed valve open,

fill heater with water. When water flows from bleed

valve, shut off water. Close bleed valve. Carefully

fill the rest of the system, making sure to eliminate

any entrapped air by using high-point vents. Close

feed valve. Test at standard operating pressure for

at least 24 hours.

2. Make sure constant gauge pressure has been

maintained throughout test.

3. Check for leaks. Repair if found.

Cold Water Operation

A heater operated with an inlet temperature of less

than 105ºF (41ºC) must have a manual bypass or an

approved low-temperature operation system to pre-

vent problems with condensation. A manual bypass,

shown in Fig. 15, must be piped into the system at the

time of installation. This piping is like a pri-

mary/secondary boiler installation with a bypass acting

as the secondary boiler piping. Raypak strongly rec-

ommends that thermometer(s) be placed into the

heater piping next to the in/out header to facilitate tem-

perature adjustment. Inlet water temperatures below

105ºF (41ºC) can excessively cool the products of

combustion, resulting in condensation on the heat

exchanger and in the flue.

CAUTION: Damaging internal condensation may

occur if the heater inlet water temperature does not

exceed 105ºF (41ºC) within 7 minutes of start-up.