Powering up the Secure Router 4134
17
ATTENTION
When powering up for the first time, Nortel recommends that you use a direct
console connection to the Secure Router 4134. After you have completed the
initial configuration, you can use a remote connection for router management.
Procedure steps (AC power)
Step
Action
1
Turn on one power switch at a time (if you installed two AC power
supplies). Power switches are on the rear panel of the Secure
Router 4134.
The fans start immediately, and the LEDs cycle.
2
Verify that diagnostic testing is underway by observing the startup
messages on your local terminal.
3
Once the router completes the self-diagnostics tests, verify that the
System LED and the power LEDs that correspond to the power
supplies installed on your router (PS0 and PS1) are green.
4
Verify that the fan LED on the rear panel of the Secure Router 4134
is green, and air is flowing through the unit.
—End—
Procedure steps (DC power)
Step
Action
1
Turn on the DC power source.
The fans start immediately, and the LEDs cycle.