Installation

11

5. Prepare the UPS or battery

cabinet (the “equipment”) for

rack mounting by following

instructions in the

equipment’s user manual. The

equipment may require

additional parts to be added or

parts to be removed for rack

mounting. After it is prepared,

lay equipment in rack-

mounting position. Fasten

inner members from Step 2 to

the equipment on both sides

as shown in the figure at right with (8) M4 screws provided in this

kit. Make sure retaining latch is near the rear of the equipment as

shown in the figure at right.

6. Open grease packet

provided in this kit. Apply

a 1" long bead of grease

four (4) places inside the

bottom, curved tracks of

front members as shown at

right. The grease will allow

the equipment to slide into

the bracket assemblies

more easily.

7. Insert the equipment, with inner members attached from Step 5,

into bracket assemblies by inserting top and bottom edges of inner

members into the top and bottom, curved tracks of front members

and sliding the equipment into rack (see figure in Step 6). Ends of

inner members are tapered to allow rear of the equipment to be

angled upward before insertion, if space allows.
Then the rear, bottom edges of inner

members can be placed into front

edge of bottom tracks, and the front of

the equipment can be tipped up into

horizontal position to insert the top

edges of inner members before sliding

the equipment into rack (see figure at right). The equipment

should move smoothly into bracket assemblies. If not, recheck

alignment of front and rear members from Steps 3 and 4.

!

CAUTION

Lifting equipment into rack may be a two-person job,

depending on weight of equipment. See equipment’s user

manual.

UPS or battery

cabinet

Front

M4 screws

M4 screws

Retaining latch

UPS or

battery

cabinet

Apply

grease

(inside)

Apply

grease