49
1. Route the team cables through the cable glands
(A).
2. Tighten the cable gland (A).
3. Connect the team cable (L+) to L+ on the busbar.
4. Connect the team cable (L-) to L- on the busbar.
☑ The team cables are connected.
5.9.3 Team Cables for Sunny Central 350
Internal team cabling in the Sunny Central 350 is already completely connected when it leaves the
plant.
Notice!
Air permeable cable ducts cause corrosion in the Sunny Central.
• Tighten the cable gland sufficiently.