7  Preparing the Multicluster System for Commissioning

Operating Manual

GRID-BOX-12-3-20-BE-en-10

21

7 Preparing the Multicluster System for Commissioning

Requirements:

☐ The Grid Connect Box must be properly installed (see Section 5, page 14).
☐ All power cables must be correctly connected (see Section 6, page 17).
☐ All control cables must be correctly connected (see Section 6.5, page 19).
☐ All cables must be tightly enclosed by the membrane at the bottom of the Grid Connect Box.
☐ All power cables must be retained inside or outside the Grid Connect Box.
☐ The floor of the Grid Connect Box must be closed with the base plates. All seals must fit properly.
☐ The kick plates must be attached to the base of the Grid Connect Box (see Section 6.6, page 20).

Procedure:

1. Mount the protective cover (see Section 9.2, page 24).
2. Close the Grid Connect Box.
3. Make sure that the conditions for commissioning the Multicluster Box are fulfilled (see operating manual of

Multicluster Box).