beautypg.com

Prepare jobsite, Dig installation pit, P80/pp25 operator’s manual – Ditch Witch P80 User Manual

Page 34

background image

P80/PP25 Operator’s Manual

Prepare - 33

Prepare Jobsite

CMW

Prepare Jobsite

Dig Installation Pit

Launch rod deep enough to prevent soil mounding. As a general rule, allow one foot of depth for every
inch of rod diameter.

If a trench box is used, depth is limited by soil type according to the US Department of Labor Regulations,
Part 1926, Subpart P. This document is available from the US Government Printing Office, 202-783-3238.

Installation Pit:

Must be in line with bore path. For bore to be successful, first rod must be straight.

Sloped back end aids new product installation. Consider new product bend radius.

To prevent bending or straining rod, position rod pusher for straight entry.

Jobsite hazards could cause death or serious injury. Use

correct equipment and work methods. Use and maintain proper safety
equipment.

NOTICE:

Cutting high voltage cable can cause electrocution. Expose lines by hand before digging.

All vegetation near operator’s station must be removed. Contact with trees, shrubs, or weeds during
electrical strike could result in electrocution.

Soil Type

Maximum Depth

A

18 ft (5.5 m)

B

10 ft (3.0 m)

C

5 ft (1.7 m)