Plan Bore Path
CMW
Plan Bore Path
Plan the bore path, from entry to end, before job begins. Locate the entire route of the material to be
installed to ensure a straight path. For complicated bores, consult an engineer. Have jobsite surveyed and
bore path calculated. Expose all crossing or parallel utilities within 18” (500 mm) of the material being
installed.
Mark Bore Path
Mark your planned bore path with flags or paint.
Select Start and End Points
Select one end of the jobsite to use as a starting point. If trench box is used, it can be placed in middle of
bore path and rod can be pushed or pulled both directions, then joined.
Consider the following when selecting a starting point:
•
Slope. consider how slope will affect boring unit set-up and bending rod.
•
Traffic. Vehicle and pedestrian traffic must be at a safe distance from equipment. Allow at least 10 ft (3
m) buffer zone around equipment.
•
Space. Check that starting and eding points allow enough space for gradual rod bending.
•
Comfort. Consider shade, wind, fumes, and other site features.