beautypg.com

Carrier 39LB User Manual

Page 15

background image

15

When a water coil is applied downstream of a direct-

expansion (DX) coil, a freeze-up thermostat must be installed

between the DX and water coil and electrically interlocked to

turn off the cooling to prevent freeze-up of the water coil.

For outdoor-air application where intermittent chilled water

coil operation is possible, one of the following steps should be

taken:
• Install an auxiliary blower heater in cabinet to maintain

above-freezing temperature around coil while unit is

shut down.

• Drain coils and fill with an ethylene glycol solution suit-

able for the expected cold weather operation. Shut down

the system and drain coils. See Service section, Winter

Shutdown, page 30.

STEAM COILS — When used for preheating outdoor air in

pressure or vacuum systems, an immersion thermostat to con-

trol outdoor-air damper and fan motor is recommended. This

control is actuated when steam supply fails or condensate tem-

perature drops below an established level, such as 120 to 150 F.

A vacuum breaker should also be used to equalize coil pressure

with the atmosphere when steam supply throttles close. Steam

should not be modulated when outdoor air is below 40 F.

On low-pressure and vacuum steam-heating systems, the

thermostat may be replaced by a condensate drain with a ther-

mal element. This element opens and drains the coil when con-

densate temperature drops below 165 F. Note that condensate

drains are limited to 5 psig pressure.
INNER DISTRIBUTING TUBE STEAM COILS — The

inner distributing tube (IDT) steam coil used in the Carrier

39M air-handling units has an inner tube pierced to facilitate

the distribution of the steam along the tube's length. The outer

tubes are expanded into plate fins. The completed assembly

includes the supply and condensate header and side casings

which are built to slant the fin/tube bundle back toward the

condensate header. The slanting of the assembly ensures that

condensate will flow toward the drains. This condensate must

be removed through the return piping to prevent premature

failure of the coil. The fin/tube bundle is slanted vertically for

horizontal airflow coils, and horizontally for vertical air-

flow coils.
IDT Steam Coil Piping — The following piping guidelines

will contribute to efficient coil operation and long coil life:

1. Use full size coil outlets and return piping to the steam

trap. Do not bush return outlet to the coil. Run full size to

the trap, reduce at the trap.

2. Use float and thermostatic (F & T) traps only for conden-

sate removal. Trap size selection should be based on the

difference in pressure between the steam supply main and

the condensate return main. It is good practice to select a

trap with 3 times the condensate rating of the coil to

which it is connected.

3. Use thermostatic traps for venting only.
4. Use only

1

/

2

-in., 15-degree swing check valves installed

horizontally, piped open to atmosphere, and located at

least 12 in. above the condensate outlet. Do not use

45-degree, vertical lift and ring check valves.

5. The supply valve must be sized for the maximum antici-

pated steam load.

6. Do not drip steam mains into coil sections. Drip them on

the pressure side of the control valve and trap them into

the return main beyond the trap for the coil.

7. Do not use a single trap for two or more coils installed in

series. Where two or more coils are installed in a single

bank, in parallel, the use of a single trap is permissible,

but only if the load on each coil is equal. Where loads in

the same coil bank vary, best practice is to use a separate

trap for each coil.

Variation in load on different coils in the same bank may

be caused by several factors. Two of the most common

are uneven airflow distribution across the coil and stratifi-

cation of inlet air across the coil.

8. Do not try to lift condensate above the coil return into an

overhead main, or drain into a main under pressure with a

modulating or on/off steam control valves. A pump

and receiver should be installed between the coil conden-

sate traps and overhead mains and return mains under

pressure.

9. Use a strainer (

3

/

32

-in. mesh) on the steam supply side,

as shown in the piping diagrams, to avoid collection of

scale or other foreign matter in the inner tube distributing

orifices.

NOTE: IDT coils must be installed with the tubes draining

toward the header end of the coil. Carrier's IDT steam coils

are pitched toward the header end as installed in the unit.

10. Ensure the AHU (air-handling unit) is installed level to

maintain the inherent slope. Also ensure the unit is in-

stalled high enough to allow the piping to be installed cor-

rectly, especially the traps which require long drip legs.

11. Do not fail to provide all coils with the proper air vents to

eliminate noncondensable gasses.

12. Do not support steam piping from the coil units. Both

mains and coil sections should be supported separately.

IDT Steam Coil Installation — Refer to drawings to position

the coils properly with regard to the location of the supply and

return connections. Ensure that the IDT coil is pitched with the

tubes draining toward the header. Carrier’s AHUs provide

proper coil pitch when the AHU is installed level.

Refer to schematic piping diagrams and piping connection

notes for the recommended piping methods.

NOTES:

1. Flange or union is located to facilitate coil removal.
2. Flash trap may be used if pressure differential between steam

and condensate return exceeds 5 psi.

3. When a bypass with control is required.
4. Dirt leg may be replaced with a strainer. If so, tee on drop can

be replaced by a reducing ell.

5. The petcock is not necessary with a bucket trap or any trap

which has provision for passing air. The great majority of high
or medium pressure returns end in hot wells or deaerators
which vent the air.

Fig. 18 — Low, Medium or
High Pressure Coil Piping

This manual is related to the following products: