Commissioning

9

3

Commissioning

3.1

Scope of delivery

! BYK LC 4 hand-held meter
! Sensor module (TetraCon V)
! Accompanying documents:

– Manual for commissioning

– Short instructions to be glued in the lid of the case

– CD-ROM with a description of all instrument functions

! Transport case with insert

3.2

Initial commissioning

Perform the following activities:

! Connect the sensor module to the meter (see section 3.3)
! Switch on the meter (see section 4.2)
! Set the date and time (see section 4.10.1)
! Calibrate the meter with the sensor module (see section 4.4)