beautypg.com

5 putting into operation, 1 installation site, 2 electrical connections – BUCHI Multivapo P-12 User Manual

Page 38: Putting into operation 5.1, Installation site, Electrical connections, 5putting into operation

background image

5 Putting into operation

38

Multivapor™ Operation Manual, Version E

5

Putting into operation

This chapter describes the installation of the Multivapor and gives instructions on initial start-up.

NOTE
Inspect the instrument for damages during unpacking. If necessary, prepare a status report imme-
diately to inform the postal company, railway company or transport company. Keep the original
packaging for future transport.

5 .1

Installation site

Place the instrument on a stable, horizontal surface and consider the maximum product dimensions.

NOTE
The shaking platform moves horizontally in an orbital manner with up to 485 rpm (for the P-12) which
may lead to considerable shaking of the surface. For this reason ensure that the surface is stable.
It is not necessary to place the instrument in a fume hood, however, the exhaust gas from the vacuum
pump should be directed toward a fume hood.

5 .2

Electrical connections

NOTICE

Risk of instrument damage by wrong mains supply.
• External mains supply must meet the voltage given on the type plate
• Check for sufficient grounding

This manual is related to the following products: