SEQUENCE OF OPERATION

Sequence of Operation- Double Element, Non-Simultaneous Operation, Single Phase, Off Peak.

Some electric utility companies will offer discounts for using electricity during “Off Peak” Times of the day. The system

allows the use of an “Off Peak” meter, which interrupts power to the lower element during high power demand periods.

Line voltage is applied across terminals

L1 & L3 of the upper thermostat. Line voltage from

off peak meter is supplied to terminal L1 of lower

thermostat. ECO in the upper thermostat is closed,

so there is voltage at terminal L4 of upper

thermostat and to one side of the upper element.

Tank is cold therefore both thermostats

are closed at terminal T2 (calling for heat). The

circuit is complete through the upper thermostat

only, allowing current to flow through upper

element.

1

2

When upper thermostat is satisfied, it opens at

terminal T2 interrupting current flow through upper

element, and closes at terminal T4 allowing voltage

to pass to one side of the lower element. This

completes the circuit through the lower thermostat

and off peak meter allowing current flow through

lower element.

3

When the lower thermostat is satisfied, it opens at

terminal T2 interrupting current flow through lower

element. The system is now in stand-by mode

waiting for the next call for heat

4

During peak power demand periods as determined

by the local utility, the off peak meter will interrupt

power to terminal L1 of lower thermostat. Only the

top thermostat/element combination is allowed to

operate during this period.

5

ECO

Closed

From

Off Peak

Meter

1

2

Thermostat closed

at terminal T2

3

Thermostat closed

at terminal T4

From

Off Peak

Meter

4

5

Thermostat closed

at terminal T2

Thermostat closed

at terminal T2

Thermostat open

at terminal T2

Off Peak

Power interrupted

Thermostat closed

at terminal T2

Page 11

11