Table of Contents
Important Safety Information ......................................1
Anhydrous Ammonia Safety...........................................1
Safety Decals .................................................................9
Introduction ................................................................18
Description of Unit ........................................................18
Using This Manual........................................................19
Owner Assistance ........................................................20
Application Overview.................................................21
Anhydrous: System Components.................................21
System Narrative ..............................................22
Conventional Liquid: Applicator System Components .28
Hydraulic Drive System Components (Options) .......28
Ground Drive System Components (Options) ..........29
Liquid System Narrative ...........................................30
Trailing Nurse Tank Components.................................33
Nutri-Pro
®
Rear Hitch (Option) .....................................33
Hitch (Option) and Nurse Tank Components (User-Pro-
visioned) ...........................................................34
Preparation and Setup ...............................................35
Initial Setup...................................................................35
Post-Delivery/Seasonal Setup......................................35
NP3000A: Get Expert Advice .......................................36
Pre-Application Setup...................................................36
Hitching Tractor to Applicator .......................................36
2-Point Hitching ........................................................37
NP3000A: Emergency Shut-Off Rope ......................38
Electrical Hookup......................................................40
Hydraulic Hose Hookup............................................41
Leveling Implement ......................................................43
Meter / Variable Rate Setup (Option) ...........................44
SCS 450 Setup Data ............................................46
Wash Water..................................................................46
Sealer Setup (NP3000A)..............................................46
Operating Instructions...............................................47
Pre-Start Checklist .......................................................47
Raising/Lowering Applicator.........................................48
Raise/Lower .............................................................48
Raising (Field, Unfolded) ......................................48
Raising (When Folded).........................................48
Lowering (Field, Unfolded) ...................................49
Lower (Service/Parking, Folded) ..........................49
Lift Cylinder Locks ....................................................50
Unfolding and Folding ..................................................51
Unfolding ..................................................................51
Unfolding (At Field)...............................................51
Unfolding (Service) ...............................................51
Folding..................................................................52
Transport...................................................................... 53
Transport Steps........................................................ 54
Final Applicator Setup .................................................. 54
NH
Operations ............................................................ 55
3
Nurse Tanks ..................................................... 55
3
: Safing Applicator Before Cart Hitch................. 55
3
: Check Hydrostatic Relief Valves ..................... 56
3
: Close Bleed Valves ......................................... 56
3
: Check Hose Discharged.................................. 56
3
: Hitching Nurse Tank ........................................ 57
3
: Mechanical Cart Hitching............................. 57
3
: Making Nurse Tank Connections .................... 58
3
: Connect Cart Hose ...................................... 59
3
: Dry Run ........................................................... 59
3
: Pass Planning.................................................. 60
3
: Start of Pass Planning ................................. 60
3
: Monitor Operation............................................ 61
3
: Field Application .............................................. 61
3
: Starting Tank Flow....................................... 61
3
: Starting Application...................................... 62
3
: Suspending Application ............................... 63
3
: Field Turns................................................... 63
3
: Stopping Application .................................... 64
3
: Breakaway Event............................................. 65
3
: Unhitching Nurse Tank .................................... 67
3
: Exchanging Nurse Tanks ............................ 67
3
: Final Nurse Tank Unhitch ............................ 67
Liquid Operations ......................................................... 68
Liq: Filling On-Board Tanks...................................... 68
Liq: Tank Quick-Fill .............................................. 68
Liq: Tank Lid Fill ................................................... 69
Liq: Hitching Conventional Nurse Tank.................... 70
Liq: Ground Drive Pump Start-Up ............................ 71
Liq: Prime the Ground Drive System.................... 71
Liq: Hydraulic Drive Start-Up.................................... 71
Liq: Field Operations (Either Pump)......................... 71
Liq: Fertilizer Operation............................................ 72
Liq: Monitor Operation (Option)................................ 73
Suspending Application............................................ 73
Liq: Stopping Application.......................................... 73
Field Set-Up Checklists................................................ 74
Field Operation Checklists ........................................... 76
Short-Term Parking...................................................... 77
Long-Term Storage ...................................................... 77
Adjustments ............................................................... 78
Row Adjustments ......................................................... 79
Anhydrous Coulter Application Depth ...................... 79
3
Sealer Adjustments .......................................... 80
Terra-Tine™ Adjustments (Option) .......................... 81