Installing the fd86n enclosure, Chapter – Rockwell Automation FD86N Drive Systems Enclosure Hardware User Manual
Page 15
Publication S-3062 – November 1997
Chapter
2
Installing the FD86N Enclosure
Introduction
This chapter provides procedures for unpacking and installing the
FD86N enclosure. It also provides procedures for fastening enclosures
together, installing conduit, and installing bus assemblies, pull boxes,
equipment enclosures, and air conditioning units to the enclosure.
Before You Begin
Before you begin enclosure installation, be sure to have:
•
For skid hardware: Socket or box wrenches for
″
hardware.
•
For all enclosure hardware: Drive bit for recessed 6-lobe, Torx™
type screw.
Unpacking the Enclosure
Do not remove the enclosure’s protective wrapping until it reaches its
final installation site. If packing must be removed for acceptance
inspection, reinstall and reseal the packing after inspection.
Note: When removing the protective wrapping, avoid marring the
enclosure surface.
While removing packing materials, find and save the packing slip.
Handling the Enclosure
FD86N enclosures are shipped on individual skids that have forklift
access. Do not remove skids until the equipment reaches its final
installation site and is ready to be lifted into position for anchoring.
Storing the Enclosure
The FD86N enclosure must be kept upright and under protective cover.
Shipping coverings are not suitable for outdoor or unprotected storage.
3
8
⁄
!
ATTENTION: Ensure that the load rating of the
lifting device is sufficient to safely handle the load.
Refer to the shipping weights on the packing slip.
!
ATTENTION: If the enclosure is removed from
the skids for storage, brace and block the enclosure
until it is permanently secured.