Titus Atlas Operating Room Ceiling System (AORCS) User Manual

Page 9

background image

I N S T A L L A T I O N & O P E R A T I O N M A N U A L

Atlas Ceiling System IOM

Installation & Operation

AORCS

Leveling


Finish the leveling procedure once the ceiling is in place, locked into perimeter members, and properly secured to each connection. Use a laser or
leveling device to adjust the hangers to the laser and wrap the support wires using no less than three full wraps within a 3 inch length on main tee
to wire connection. Local kinks or bends are not an acceptable means for leveling the grid.

Confirm all MEP trades, all above ceiling work, and all inspections are complete before proceeding to next step.

Wipe all dust, dirt and construction debris from the top of the ceiling tee flanges. Install the ceiling gasket provided with the ceiling system, making
sure it adheres tightly to the tee flange. Do not leave any gaps between the main tees to cross tees or cross tees to wall molding.