3 auspacken und aufstellen, Unpacking and installation, Instrument setup – Leica Biosystems EG1150 C User Manual
Page 13: 3 unpacking and installation

13
Leica EG1150 C
4. Instrument Setup
4.3 Unpacking and installation
The unpacking instructions are located on the outside of the transport box in which the
instrument is delivered shows the assembly of the original packaging.
The numbers indicate the sequence of disassembling and reassembling.
When the instrument is delivered, check the tilt indicators on
the packaging.
If the arrowhead is blue, the shipment was transported laying
flat, was tilted at too great an angle or fell over during transport.
Note this on the shipping documents and check the shipment
for possible damage.
Fig.
4
1
2
3
4
6
5
3
6
1. Remove and lift off 8x screws (1) for the
lid (2).
2. Remove upper pad (3).
3. Remove the accessories (4).
These unpacking instructions
only apply if the box is placed
with the symbols
facing
upwards for unpacking.
The Leica EG1150 C always has
to be transported upright and
horizontally. It must not be in-
verted under any circumstances,
even for short periods, or stored
on one of its sides.
It is mandatory to observe a
waiting time of 4 hours between
the last transport and the first
time the instrument is switched
on. The compressor oil moved
during transport must be able
to flow completely back into its
original position.