Code 33 - reserved, Code 34 - p2-auxiliary #1 - inhibit, Code 35 - p2-auxiliary #1 - tie down – JLG 10MSP Service Manual User Manual
Page 135: Code 36 - reserved, Code 37 - reserved, Code 34 - p2-auxiliary #1 - inhibit -31, Code 35 - p2-auxiliary #1 - tie down -31, See table 6-32, Ge 6-31, See table 6-33
SECTION 6 - TROUBLESHOOTING
3121228
– JLG Lift –
6-31
Code 33 - RESERVED
Code 34 - P2-Auxiliary #1 - Inhibit
Check For These Obvious Conditions First:
• Platform Gates Closed.
• Pressure on the Platform Footswitch (after power up).
NOTE: In the procedures below, if you check continuity between pin 6 and 16 it should show open circuit, when the platform
gates are closed and nothing is on the foot switch. When you step on the foot switch with the gates closed, you should
see a closed circuit.
Code 35 - P2-Auxiliary #1 - Tie Down
Check For These Obvious Conditions First:
• Pressure on the Platform Footswitch during machine power up.
NOTE: In the procedures below, if you check continuity between pin 6 and 16 it should show open circuit, when the platform
gates are closed and nothing is on the foot switch. When you step on the foot switch with the gates closed, you should
see a closed circuit.
Code 36 - RESERVED
Code 37 - RESERVED
Table 6-32. Code 34 - P2-Auxiliary #1 - Inhibit
STEP
ACTION
SPEC
YES
NO
1.
At the Ground Control Module, P2 connector, check the voltage across
pins-16 (orange/red 49-5) and 6 (black 12) is reading within specification?
0 - 2V DC
Go to Step 2
Replace Ground
Control Module
2.
Remove the P2 connector from the Ground Station Module; check continu-
ity of the individual wires in the platform harness. (P2 to platform junction
box),
—
Go to Step 3
Repair or
Replace Platform
Harness
3.
Check continuity of gate switches and foot switch circuit. (Switches are
wired in series; doors shut and foot switch depressed, circuit will be
closed)
Consult Factory
Replace Compo-
nent or Repair
Wires
Table 6-33. Code 35 - P2-Auxiliary #1 - Tie Down
STEP
ACTION
SPEC
YES
NO
1.
At the Ground Control Module, P2 connector, check the voltage across
pins-16 (orange/red 49-5) and 6 (black 12) is reading within specification?
0 - 2V DC
Go to Step 2
Replace Ground
Control Module
2.
Remove the P2 connector from the Ground Station Module; check continu-
ity of the individual wires in the platform harness. (P2 to platform junction
box),
—
Go to Step 3
Repair or
Replace Platform
Harness
3.
Check continuity of gate switches and foot switch circuit. (Switches are
wired in series; doors shut and foot switch depressed, circuit will be
closed)
Consult Factory
Replace Compo-
nent or Repair
Wires