beautypg.com

Floating ridge – Mueller Snap Lock (MSL) User Manual

Page 22

background image

22

FLOATING RIDGE

Installation Steps: (use only with fixed eave and valley)

1. Slide the backup channel underneath the end of the panel as shown.

2. To accommodate the width of the Ridge Trim, apply the butyl tape sealant across the pan of the panel,

aligned over the backup channel.

3. Install the end dam using #12 screws on 4” centers through the panel and the backup channel as shown.

4. Use tube sealant to seal the ends of the end dam.

5. Apply butyl tape sealant to the top of the end dam.

6. Fasten Ridge trim to end dam using #14 x 7/8 Lap screws on 6” centers.

#12 x 1 1/4" Self Drill

Ridge Screw Sequence

Clip

Mueller Snap

Lock Panel

Tube Sealant on

Vertical Edges

Ridge Trim

Back Up Channel

#10 x 1" Pan Head

Self Drilling Screw

End Dam

#14 x 7/8" Lap

Tek Screw

6"

6"

2"

Tek Screw with Washer

Purlin

Purlin

2" Minimum Clearance

Tape

Sealant