1. Equipment Inspection

Check all equipment for completeness against the order and for any evidence of shipping damage.
Shortages or damage must be reported immediately to the carrier and your authorized representative or
distributor of PULSA GLM

®

pumps.

Included Items:
• PULSA GLM® Metering Pump with Motor Adaptor

Optional Items:
• Motor (pre-installed at the factory)
• Foot Valve Kit (provided on PULSA GLM® models M1 and M2 only).

2. Installation

2.1

Location

When selecting an installation site or designing a chemical feed system, plan for operation and routine
maintenance. Provide 1M (3.25FT) of space around the pump for this purpose.

PULSA GLM

®

pumps are designed to operate in an environment where the pump is protected from direct

sunlight, and precipitation (i.e., under shelter). The ambient temperature must be between 0

° C (32° F)

and 40

° C (104° F). If necessary add environmental controls.

The pump must be rigidly bolted to a solid and flat foundation to minimize vibration and prevent
loosening of the connections. The pump must be level within 5

° to assure proper check valve operation.

2.2

Motor

The PULSA GLM® is typically shipped with the motor pre-installed. It must be wired in accordance with
local and national requirements by a qualified electrician. Please refer to the motor nameplate for further
manufacture specific information.

If the PULSA GLM® was purchased less motor, please refer to section 5.4 Motor Installation for further
instructions.

Figure 1: Foot Valve Kit