2. Hardware Installation

Do not install near power lines. If any part of the tower

comes in contact with power lines you could be KILLED.

Contact local utilities for the location of buried utility

lines before digging or driving grounding rods.


Do not fit the 3 meter ET Tower sections together until the

appropriate time. Once attached, they cannot be detached.

The ET Tower provides a support structure for mounting the ET107 weather

station components. FIGURE 2-1 shows a typical ET Tower installation

option. The tower is designed to withstand winds of 100 mph. The lightning

rod assembly is attached after the instrumentation enclosure is installed.

FIGURE 2-1. ET tower installation with currently-available AC power

option

User supplies valve box at base of station and weatherproof

enclosure for transformer. See FIGURE 2-1.

The AC power supply option at one time included a step-down

transformer instead of the power supply. Appendix E, Step-down

Transformer Installation, provides information about using the

step-down transformer.