iv
InfraStruXure Site Planning, Installation, Start-Up
Ensure Total Power Off . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
Connect the Power Source to the PDU . . . . . . . . . . . . . . . . . . . 13
Access the PDU Main Input switch
. . . . . . . . . . . . . . . . . . . 13
Attach conduit to the PDU for the input conductors
. . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Route the input conductors to the main input circuit switch
. 15
Torque specifications and tools required
. . . . . . . . . . . . . . . 15
. . . . . . . . . . . . . . . . . . . . . . . . 16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
How to connect contacts to the PDU Monitoring Unit
. . . . . . 18
Shielding Troughs and Shielding Partitions for overhead
wiring along rows
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
Cable Ladders for overhead wiring across rows
Install InfraStruXure Rack-Mount Devices . . . . . . . . . . . . . . . . . 21
Install the Rack Automatic Transfer Switches (ATS)
Install the Rack Power Distribution Units (PDU)
Install the InfraStruXure Manager and Hub (or Switch)
. . . . . 21
Install the APC Environmental Monitoring Unit
Route and Attach Overhead Wiring . . . . . . . . . . . . . . . . . . . . . 22
Route and attach power cables to equipment racks
Wiring Under the Floor (Alternative) . . . . . . . . . . . . . . . . . . . . 25
Connect network cables to InfraStruXure components
. . . . . 27
Route network cables to the InfraStruXure
Manager hub (or switch)
. . . . . . . . . . . . . . . . . . . . . . . . . 28
Start-Up Procedure ................................................ 29
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29