Installation Procedures: Wiring Under the Floor (Alternative)

26

InfraStruXure Site Planning, Installation, Start-Up

4. At the circuit breaker panel,

cut the wires to the proper
length, and connect the
power cable’s individual
wires:

a. If you have branch

current monitoring

installed, route each

phase conductor through

a current sensor. If it is a

multi-circuit cable, route

the L1, L2, and L3 wires

through separate current

sensors.

b. Connect the L1, L2, and

L3 wires to the circuit

breaker(s). The

illustration at right

shows a single-circuit

cable connecting to a

single-pole breaker;

however, you can also

connect a multi-circuit

cable to a four-pole

breaker.

c. Connect the neutral wire

to the closest open termination point on the Neutral Bar.

d. Connect the PE wire to the closest open termination point on the PE Bar.

5. Connect the neutral wire to the neutral bar and the PE wire to the isolated ground bar.