How to Apply Power to the System

1. Close (turn ON) the main circuit breaker of the

power source supplying power to the PDU.

2. Close (turn ON) the main input on the PDU.

3. Power the PDU distribution circuit breakers.

a. Set the Main Output circuit breaker on the PDU

to ON.

Note: After the Main Output circuit breaker has

been closed, both PDU distribution panels will be

energized.

b. Close (turn ON) the PDU distribution panel circuit breakers.

When the distribution panel circuit breakers are closed, the PDU power cables