Installation instructions, Under-cabinet installation, 4 install side “l” brackets – GE ZV800SJSS User Manual
Page 21: 3 cut the opening, 5 remove side screw
21
Installation Instructions
4 INSTALL SIDE “L” BRACKETS
Install the “L” brackets onto each side of the
cutout. The wide flat portion should be on top of
the opening. Install 2 screws into the top of each
bracket.
Install 2 screws in
each bracket
UNDER-CABINET INSTALLATION
3 CUT THE OPENING
If the cabinet has been installed, remove it from the
wall.
Use the Top Cabinet Template to locate and cut a
hole in the bottom of the cabinet.
If necessary, place the template on top of the
cabinet to accurately cut a matching hole.
Install the cabinet onto the wall.
The cabinet must be firmly secured to the wall and
be capable of supporting 100 lbs.
INSTALL WOOD BLOCKS IF NECESSARY
Install filler blocks whenever the cabinet frame hangs
below the cabinet bottom.
Install filler blocks whenever the cabinet bottom is
less than 3/4” thick.
Install the filler blocks on each side of the cutout. The
filler blocks will accept the hood mounting screws.
NOTE: Additional filler blocks may be required along
the outside edges to accept the outside screws. See
Step 5.
IMPORTANT: If filler blocks are not used, the hood may
not be secured to the cabinet.
Cabinet Frame.
Cabinet Bottom Shelf
Filler Block
Top of Vent
Hood
Equivalent
to Depth of
Cabinet Recess
5 REMOVE SIDE SCREW
The top center screw on both sides of the hood
can be used to close up any noticeable gaps at the
outside edges. See illustration.
Remove the center screw cover and screw on each
side as shown.
Remove screw cover
and screw