Installation Instructions

4 INSTALL SIDE “L” BRACKETS

‡ Install the “L” brackets onto each side of the

cutout. The wide flat portion should be on top of

the opening. Install 2 screws into the top of each

bracket.

Install 2 screws in

each bracket

UNDER-CABINET INSTALLATION

3 CUT THE OPENING

If the cabinet has been installed, remove it from the

wall.
‡ Use the Top Cabinet Template to locate and cut a

hole in the bottom of the cabinet.

‡ If necessary, place the template on top of the

cabinet to accurately cut a matching hole.

‡ Install the cabinet onto the wall.
The cabinet must be firmly secured to the wall and

be capable of supporting 100 lbs.

INSTALL WOOD BLOCKS IF NECESSARY

‡ Install filler blocks whenever the cabinet frame hangs

below the cabinet bottom.

‡ Install filler blocks whenever the cabinet bottom is

less than 3/4” thick.

‡ Install the filler blocks on each side of the cutout. The

filler blocks will accept the hood mounting screws.

NOTE: Additional filler blocks may be required along

the outside edges to accept the outside screws. See

Step 5.

IMPORTANT: If filler blocks are not used, the hood may

not be secured to the cabinet.

Cabinet Frame.

Cabinet Bottom Shelf

Filler Block

Top of Vent

Hood

Equivalent

to Depth of

Cabinet Recess

5 REMOVE SIDE SCREW

The top center screw on both sides of the hood

can be used to close up any noticeable gaps at the

outside edges. See illustration.

‡ Remove the center screw cover and screw on each

side as shown.

Remove screw cover