Suspended Ceiling Tile (Plenum) Mount Instructions
2
Brocade Mobility 1240 Access Point Installation Guide
19
53-1002917-01
a. Connect a RJ-45 CAT5e (or CAT6) Ethernet cable between the power over
Ethernet switch port and the access point’s GE1/POE port.
b. Ensure the cable length from the Ethernet source (host) to the power over
Ethernet and access point does not exceed 100 meters (333 ft).
For standard power adapter (non power over Ethernet) and line cord
installations:
a. Connect a RJ-45 Ethernet cable between the network data supply (host)
and the access point’s GE1/POE or GE2 port.
b. Verify the power adapter is correctly rated according to the country of
operation.
c. Connect the power supply line cord to the power adapter.
d. Attach the power adapter cable into the power connector on the access
point.
e. Attach the power supply line cord to a power supply.
CAUTION
If not using power over Ethernet, ensure only the Mobility 1240 Access
Point’s designated power supply (PWRS-14000-247R) is used to supply
power to the access point. Using an incorrectly rated power supply
could damage the access point and void the product warranty. Do not
actually connect to the power source until the cabling portion of the
installation is complete.
14. Verify the behavior of the access point LED light pipe. For more information on
Mobility 1240 Access Point LED behavior, see
15. Place the ceiling tile back in its frame and verify it is secure.
16. The access point is ready to configure.