System Installation
System Installation Checklist
The line monitoring system should be installed in the following order.
1.
Install dispensers and controlling console according to
manufacturer’s specifications. Test dispensers with console for
proper operation. See System Installation Requirements on
following page.
2.
Install Tank Monitor System according to manufacturer’s
specifications. See System Installation Requirements on
following page.
3.
Mount RLM. Refer to RLM General Installation section of this
manual.
4.
Connect system components to specific dispenser box (DBox).
See Pump Specific Installation section for the appropriate brand
of dispenser.
5.
Test RLM with Tester Program. Refer to Diagnostics section of
this manual.
6.
Connect to Tank Monitoring System and test fully integrated
system.