Installation of Model 3010PAC Analyzers includes:
1. Unpacking, mounting, and interconnecting the Control Unit and
the Analysis Unit
2. Making gas connections to the system
3. Making electrical connections to the system
4. Testing the system.
This chapter covers installation of the Control Unit. (Installation of
the Analysis Unit is covered in Part II of this manual.)
3.1
Unpacking the Control Unit
The analyzer is shipped with all the materials you need to install and
prepare the system for operation. Carefully unpack the Control Unit and
inspect it for damage. Immediately report any damage to the shipping
agent.
3.2
Mounting the Control Unit
The Model 3010PAC Control Unit is for indoor use in a general
purpose area. It is NOT for hazardous environments of any type.
The standard model is designed for flush panel mounting. Figure 3-1
is an illustration of a Model 3010PAC standard Control Unit front panel
and mounting bezel. There are four mounting holes—one in each corner of
the rigid frame. Drawing number D-64596, at the back of this manual,
contains a panel cutout diagram.
On special order, a 19" rack-mounting can be provided. Per order, one
or two 3010PAC series Control Units are flush-panel mounted on the 19"