Patriot Putty Unit Operations Manual

Rev. 08/2012

Page | 29

5.

Adjust pressure regulator marked Air Life to 20 psi

6.

Hold pail down if it beings to lift, close and open the Air Lift lever intermittently to raise follower and
pump out of pail.


7.

It may be necessary to adjust both ram / Air Lift and ram extraction pressures accordingly to
necessitate removal without lifting the pail.

8.

After pump and follower are removed, inspect, seal and dispose of Plastic Boot if necessary.

9.

Clean any build up of material on seals as well as follower plate.

10.

Replace with “new” pail and refer back to procedures for priming.





















Fig. 51












Ram control valve and Ram / Air
Lift gauge and regulator.

Ram Extraction pressure
gauge and regulator