Pre Start Up Check List

PreStartUp WaterCool Rev. 0508

Project Name: _________________________ Date: ___________________

Address: _________________________

_________________________

YES NO

1

.

Are modules connected properly “per Codes and Installation Manual”?

____ ___

(Installation, Operation & Maintenance Manual is available at

www.climacoolcorp.com

)

2

.

Is there a 60-80 mesh strainer on condenser & evaporator inlet water?

____ ___

(Fill water to Chiller through upstream 60-80 mesh strainer.)

3.

Is Condenser water system filled & flushed?

____ ___

(See “Filling the Water System” in ClimaCool IO&M.)

4.

Is Chilled water system filled, flushed & all air purged from system?

____ ___

(All air must be purged from system prior to startup. See “Filling the Water System” in ClimaCool IO&M.)

5.

Are all pumps tested & operational?

____ ___

6.

Are required GPM’s being provided to Chiller?

____ ___

(See project selection and performance sheets available from ClimaCool Sales Rep.)

7.

Is required Differential Pressure being provided to Chiller?

____ ___

(See project selection and performance sheets available from ClimaCool Sales Rep.)

8.

Flow & differential switches set to trip on drop below required flows?

____ ___

(Set to trip on low flow (less than 75% flow), not pump on/off.)

9

.

Have all Chiller flange connections been leak tested?

____ ___

10.

Is there water presently circulating through chiller?

____ ___

11

.

Is power and control wiring complete to each module?

____ ___

(Note: All Chiller covers are removable DO NOT Attach Wiring Etc.)

12

.

Do wiring & devices meet with approved control submittal drawings?

____ ___

13

.

Is required load available to run multiple compressors at start-up?

____ ___

14

.

Is control functional to maintain condenser water temperature?

____ ___

(This includes maintaining “minimum” inlet temperature. See “Operational Limitations” in ClimaCool IO&M.)

15

. Are water quality parameters tested and in compliance with ClimaCool IO&M?

(See “Water Treatment” in ClimaCool IO&M for required Water Quality Parameters.)

If you checked “No” to any question above, provide the line reference number and the date of scheduled completion below.

Please note, all conditions must be complete prior to the start-up date.

__________________________________________________________________________________________

__________________________________________________________________________________________

__________________________________________________________________________________________

*This form must be completed and submitted to ClimaCool Corp.a minimum of two (2) weeks prior to final scheduling of

any Start-up.

Note: If any of the above items are not complete at time of start-up, backcharges will be assessed for additional costs.

Contractor Name: ___________________________ __________________________________

Address: ___________________________

(Authorized Signature)

___________________________

Phone: ___________________________ Date: _____________________________

Pre Start-Up Check List*

(Water-Cooled)